Developers intending to bid for UK Round 4 offshore wind projects liked what they saw of the Crown Estate’s plans for the tender process but have questioned the substantial deposits they need to pay in respect of sites that may not progress to the latter stages of the process
As previously highlighted by OWJ, developers seeking to lease the seabed off the coast of England, Wales or Northern Ireland for new offshore wind projects will be subject to a three-stage tender process.
The final design of the tender process, officially Offshore Wind Leasing Round 4, was presented by The Crown Estate to an industry audience in July 2019. The Crown Estates will confirm the areas of seabed being made available to market when the leasing round launches later this year but has said the rights would be capable of supporting at least 7 GW of renewable energy.
Speaking at the time the details were announced by the Crown Estate, Jonny Boston, its business development manager, said the process had been designed to be “attractive, accessible and fair.
“Our proposed tender design would assess the technical capability of potential bidders and their proposed projects, before using the option fee as a means of determining project award,” he said. “This approach will help to ensure capable bidders and the strongest possible projects come forward for new leasing, within a process that is objective, fair and transparent.”
The final design comes after 18 months of engagement by The Crown Estate with the offshore wind market and incorporates a number of changes from the original tender design. Significantly, the tender process has now been split into three stages: a pre-qualification stage (PQQ); and a two-part invitation to tender stage (ITT 1 and ITT 2).
Experts at law firm Pinsent Masons told OWJ that potential bidders will firstly be assessed on their technical competence including project management, access to grid connection and consenting and financial strength at PQQ. The project bids of developers which pre-qualify will then be assessed at ITT 1 based on project-specific financial and technical assessments. Developers can propose a ‘primary project’ and up to 20 smaller ‘secondary projects,’ overlapping with the primary project.
Projects that pass ITT 1 will move on to ITT 2, at which awards will be made based on the option fee proposed by the bidder. Projects will be awarded over a week-long bidding cycle with one project awarded daily, which The Crown Estate said would allow developers to review and adjust their bidding strategy as the process progresses.
Developers will only be permitted to bid on one project per day either on their own or as part of a consortium, with a 400 MW minimum and 1.5 GW maximum capacity proposed per project. In addition, the capacity in any one area of the seabed will be capped at 3.5 GW “to ensure geographic diversity.”
The Crown Estate will no longer require a successful developer to pay the full option fee up front. Instead, a winning bidder will be required to transfer the option fee for the first year to seabed manager by 6 pm on the day the successful bid is announced, then the following two years once the lease is signed. The balance of the option fee will then be payable annually.
Flexibility in project milestones will be welcomed by developers and stakeholders in the consent process, as in previous rounds the completion of pre-application work by developers, to the satisfaction of stakeholders, was a significant challenge.
Pinsent Masons partner Gareth Phillips said, “While the flexibility in the option fee arrangement should be more attractive to developers than under previous rounds, those that attended the event last week called for TCE to ‘think again’ in respect of the first payment being non-refundable.”
Pinsent Masons planning law expert Gary McGovern added, “Developers are effectively being asked to pay a substantial deposit in respect of a proposed site that may not progress beyond the plan-level Habitats Regulation Assessment (HRA) undertaken by TCE, a situation made less attractive by The Crown Estate having stated that sites for which an ‘Adverse Effect on Integrity’ of a protected habitat cannot be ruled out will be dropped without consideration of whether an IROPI (Imperative Reason of Overriding Public Interest) case can be made for the site to proceed.”
“To some extent this risk could be mitigated by The Crown Estate engaging developers in the HRA process to a greater degree than experienced in relation to the Offshore Wind Extension Round HRA, which should be concluded by the Crown Estate this month,” Mr McGovern explained.
A rental discount of 50% on up to 10% of the project capacity for the first five years of operation will be made available to qualifying projects, to incentivise and support developers interested in trialling new technologies. Further details will be announced at a later stage.
Project milestones in the agreement for lease awarded to a successful bidder feature greater flexibility than in previous rounds, with “significant development activity” being required within 18 months of award.
That activity could include preliminary environmental impact assessment work, such as geophysical and ornithological surveys. An application for development consent in respect of both generation and transmission assets must be submitted within five years.
“Flexibility in project milestones will be welcomed by developers and stakeholders in the consent process, as in previous rounds the completion of pre-application work by developers, to the satisfaction of stakeholders, was a significant challenge,” said Mr Phillips.
Pinsent Masons partner Alan Cook said that, overall, developers welcomed The Crown Estate’s proposals, which would give them the opportunity to prepare before the formal launch of the leasing round.
“Bidders will be required to participate in daily bid cycles under which the highest bid each day will win, with the first (non-refundable) payment of the deposit being payable that same day, and careful thought will be needed as to the best way to approach this process,” he said. However, he noted that timescales remain unclear and “we are now simply told that the Round 4 launch is proposed for later in 2019.’”
© 2023 Riviera Maritime Media Ltd.