RWE has finalised the sale of its 33.33% share in the Five Estuaries offshore windfarm to EDF power solutions UK and Ireland
Former project lead and largest stakeholder in the Five Estuaries offshore wind project RWE has sold its one-third stake to EDF, with EDF taking over responsibility for leading the project on behalf of its joint-venture partners.
RWE said it plans to reinvest the proceeds from the transaction in its existing portfolio of consented offshore wind projects. Financial terms of the sale were not disclosed.
“The priority of the Five Estuaries project is to progress its transition from development into construction and ultimately operation,” an RWE spokesperson said.
“We’re delighted that EDF, with its long-standing commitment to delivering UK renewables, is committed to maintaining the pace of the project’s ambitions, and we look forward to seeing it come to fruition in the months and years to come.”
RWE will continue working with Five Estuaries in the short term to support the transition to the new owners.
The change in ownership comes after Five Estuaries secured development consent in December 2025 from UK Secretary of State for Energy Security and Net Zero Ed Miliband.
At the time consent was granted, RWE held 33.33% of the project and was leading its development on behalf of the partners. The remaining interests were held by a Macquarie-led consortium with 25%, ESB with 20.83% and Sumitomo Corp with 20.83%.
Five Estuaries is an extension of the operational Galloper offshore windfarm and will be developed in the southern North Sea across two seabed areas covering approximately 128 km².
The consent allows for up to 79 wind turbines with a maximum tip height of 370 m, together with their foundations. Once fully operational, the project would have capacity to generate enough electricity to supply around 1M average UK households.
Electricity generated by the windfarm is planned to be brought ashore via subsea export cables at Sandy Point, between Frinton-on-Sea and Holland-on-Sea in Essex.
From the landfall, underground cables will run to a new substation west of Little Bromley before connecting with the East Anglia Connection Node on National Grid’s proposed Norwich-Tilbury transmission corridor.
The Five Estuaries development consent followed years of development work and community and stakeholder engagement. Following consent, the project was expected to refine its final design in accordance with the consent conditions and seek a route to market ahead of a financial decision and construction.
The divestment forms part of RWE’s wider approach to its offshore wind portfolio. The company said proceeds from the sale of its Five Estuaries interest will be directed towards its existing portfolio of consented offshore projects.
RWE secured Contracts for Difference for five UK offshore wind projects in Allocation Round 7, representing a combined installed capacity of 6.9 GW. The company plans to expand its global offshore wind capacity by a net 5 GW by 2031.