Shell is joining the project after Equinor bought out BP’s stake in July 2026, aiming to take it to a final investment decision in 2027
Shell is taking a 30% interest in Equinor’s Bay du Nord project offshore Newfoundland and Labrador, bringing another international energy major into the deepwater development as it moves towards a targeted final investment decision (FID) in early 2027.
Equinor will retain a 70% interest and remain operator following the transaction, which the Norwegian energy company said would strengthen the project while supporting risk sharing, capital allocation and portfolio management.
“We are pleased to welcome Shell as a partner in Bay du Nord. This is a strategic project for Equinor, with a high-quality resource base and the potential to create significant long-term value,” said Equinor executive vice president for Exploration and Production International Philippe Mathieu.
“Shell’s entry strengthens the project as we continue to mature it towards a final investment decision.”
The agreement comes three months after Equinor acquired BP’s interest in Bay du Nord, temporarily taking Equinor’s ownership of the project to 100%. At the time, Equinor said the acquisition gave it greater flexibility to "mature the development" while it sought opportunities to bring partners into the project.
Bay du Nord is in the Flemish Pass basin, approximately 500 km offshore Newfoundland and Labrador, and is being developed around a floating production, storage and offloading (FPSO) vessel connected to a phased subsea development.
The initial phase incorporates the Bay du Nord discovery, made in 2013, and Cambriol, discovered in 2020, in water depths ranging from 600 m to 1,170 m. Recoverable resources in the initial development are estimated at more than 400M barrels of oil, while Cappahayden, Harpoon and Baccalieu have been identified as potential future tiebacks.
Equinor has estimated investment in the development at approximately C$14Bn (US$10Bn). The project is finalising front-end engineering and design (FEED), with work focused on capital efficiency, execution planning and strengthening the overall robustness of the development.
If sanctioned on the current schedule, first oil is expected in 2031.
The project’s ownership has changed substantially since BP entered Bay du Nord in 2022 when it agreed to acquire Cenovus Energy’s 35% stake in the then-undeveloped project as part of a deal valued at about US$1Bn. The acquisition increased BP’s presence in the Flemish Pass, where it already held six offshore exploration licences, before Equinor bought BP out of Bay du Nord in July 2026.
Work has also advanced on the project’s production infrastructure. BW Offshore was selected as preferred bidder for the Bay du Nord FPSO in September 2025, signing a head of agreement with Equinor Canada covering continued technical and commercial discussions, FEED work and development of a commercial solution.
The FPSO is being designed for the harsh sub-Arctic operating environment and would have capacity to support production of up to 160,000 barrels of oil per day. The design includes a disconnectable turret system and provision for future subsea tiebacks, supporting the potential longer-term development of resources across the basin.
Emissions-reduction measures planned for the topsides include high-efficiency power generation and heat recovery, variable-speed drives and a closed flare system.
Bay du Nord has been described as Canada’s first deepwater oil project and would open a new production area offshore Newfoundland and Labrador if it proceeds.
The project traces its current ownership structure back to a period of consolidation among major offshore producers. When BP moved to acquire the 35% Cenovus interest in 2022, Bay du Nord already comprised several oil discoveries made by Equinor over the preceding decade in the Flemish Pass.
Events