Saipem said its Saipem 7000 unit is back in operation after an incident in April put it out of service temporarily
On 14 April 2022, the main block wire on one of the vessel’s cranes, Crane n.1, broke during a lifting test. The vessel had completed dynamic positioning trials and began to undertake a five-year main cranes load test, under the supervision of class society DNV. The test involved lifting barges.
The semi-submersible crane vessel is the third-largest vessel of its kind and arrived at the Seagreen windfarm field north of Edinburgh, 31 May.
Following the incident, Saipem reported Saipem 7000 “went through a first step of necessary repair works” and that Crane n.2 obtained the related certifications, allowing it to operate with a lifting capacity in line with Seagreen project technical requirements and scope of work.
At the end of 2021, Saipem 7000 completed installation of the 5,100-tonne jacket for the Seagreen offshore windfarm in Scotland. The vessel’s scope of work for the windfarm included installing 114 foundation jackets; 23 of which have been already installed, while the remaining 91 will be installed from now until year-end 2022.
Crane n.1 is expected to complete repair works to allow the vessel to return to its full lifting capacity by early 2023.
Riviera Maritime Media will provide free technical and operational webinars in 2022. Sign up to attend on our events page
Events
© 2024 Riviera Maritime Media Ltd.